Post Fixed InsulAPE
"We have a special, proprietary bonding adhesive that we use to post-fix InsulAPE to existing concrete foundations"
Our system means InsulAPE can be installed to the external face of new and existing concrete slabs in a post-fix situation. For new concrete slabs sometimes site programming, or other reasons, mean that InsulAPE cannot be be installed before the slab is going to be poured. In situations such as these we can return to site after the slab has been poured, or even after the entire house has been constructed, and retrofit InsulAPE to the edge of the slab.
We have a special, proprietary bonding adhesive that we use to post-fix InsulAPE to existing concrete foundations.
​
The profile that we use for post-fixed situations is in most situations different from the profile that we use for pre-pour installations. Therefore you cannot order a pre-pour InsulAPE product and then decide to post fix it in most cases.
Datasheet
Details
Advantages of Post Fix
The main advantages of post-fixing InsulAPE are;
-
the slab and wall framing can continue traditionally, with no potential conflicts on bottom plate bolt clearances.
-
Less chance of damage from digging required for drainage etc. The best time to install is after any scaffolding is down and cladding is fitted.
-
Ideal for external insulation systems, aligning the wall insulation to slab insulation on the same plane.
-
Continuous adhesion with a specialised plastering system for external XPS application to the concrete slab face. Where adhered to vapour control layers or other membranes, construction adhesion (water-based may be applied).
-
InslAPE Post Fix can be supplied in 300mm and 600mm heights and in 30mm, 40mm, 50mm, 75mm and 100mm thicknesses.
Disadvantages of Post Fix
Note that InsulAPE will protrude 30mm (for XPS 30mm option foam) out from the face of the concrete slab. This needs to be considered in relation to the cladding system and cavity. This may result with the top taper of InsulAPE being fixed below the finished level of the slab. This will be to allow the cavity to drain (Building Code requirement). Thermal design needs to consider the small thermal bridge at that point. Consideration regarding design and placement is required by the design/architects for the project
​
Lead Time
Please allow at least 3 weeks lead time for manufacturing once order placed.

